卫生间隔断安装方案



一、施工准备:



1、材料:按照生产部门加工好的材料进行楼层位置分类搬运好,并分好配件及铝材位置



2、配件:不锈钢材质支座,角码,拉杆铝材、不锈钢指示锁、不锈钢合页、门挡铝材、挂衣钩。



3、紧固材料:膨胀胶塞、圆头或平头自攻螺丝、玻璃胶。



4、主要工具:电钻2个、3.5钻头、螺丝批头、电源、插做、虎钳、胶锤、测量尺、玻璃胶枪等。



5、作业条件:(1)卫生间的地面材料及墙面材料安装完成。(2)施工期间保证提供相应电源。



二、工艺流程



现场放线→固定角码、脚座钻孔打眼→固定角码、脚座钻孔安装→侧板安装→立板安装→合页安装→调整门缝固定拉杆→安装门→安装指示锁及门挡安装。

浏览量:102
{"serList":[{"icon":"iconfront front-shouye","status":"1","isSys":"1","title":"首页","url":"index.html","type":"index"},{"icon":"iconfront front-pinglun","status":"1","isSys":"1","title":"留言","url":"msg.html","type":"msg"},{"icon":"iconfront front-didianmianxing","status":"1","isSys":"1","title":"地图","url":"map.html","type":"map"},{"icon":"iconfront front-weibiaoti-","status":"1","isSys":"1","title":"电话","phone":"13902896631","type":"tel","telType":"0","color":""},{"icon":"iconfront front-duanxin","status":"0","isSys":"1","title":"短信","phone":"13800138000","type":"sms"},{"icon":"layui-icon layui-icon-share","status":"0","isSys":"1","title":"分享","shareList":["weixin","weibo","qq","qqZone","douban","tieba","copy"],"type":"share"}],"hasEdit":true}